The head of “Centrenergo” was again denied promises Kasalica in terms of translation units zmiivska TPP of coal brand “G”

Commissioning works at unit No. 2 Zmiev TPP (Kharkiv region) after his transfer to the coal of the gas group will be held in the second and third quarters of this year, block No. 5 – in the third and fourth quarters, while the Minister of energy and coal industry Igor Nasalik is counting on the launch of the updated blocks at the end of March and may, respectively, said acting CEO of PJSC “Centrenergo” Oleg Kosenko.

“We plan, provided that all will go fine (the project implementation commenced, the financial plan will be approved), we will begin the implementation of this project, we projected commissioning work on the block of the station №2 in the second and third quarter, the unit station No. 5 – in the third and fourth quarter. What I’m getting at… we want autumn and winter of 2017-2018 to pass on these two units,” – said Oleg Kozemko, the TV channel NewsOne on Thursday .

He said that the physical implementation of the project on unit 5 zmiivska TPP will start from 15 April, after the end of heating season (this unit is heating).

According to Oleg Kozemko, today, a draft transfer of units No. 2 and No. 5 coal of the gas group, he passed the examination of state enterprise “Ukrwoodexport”, the final stage of working documentation development, in addition the already manufactured part of the equipment which must be mounted on the block # 2.

As reported, in mid-January of 2017, Minister of energy and coal industry of Ukraine Igor Nasalik said that unit No. 2 Zmiev TPP after conversion to coal burning gas group is scheduled to start March 20, block No. 5 – at the end of may.

In August 2016, O. Kosenko was already denied allegations I. Kasalica in terms of transfer of units No. 2 and No. 5 zmiivska TPP with coal anthracite (comes with the occupied areas of Donbass) coal gas group (available on the Ukraine-controlled territories).

In the spring of 2016, the Minister promised to run unit # 2 on the new fuel in December 2016, and unit No. 5 – in February 2017. In turn, the head of “Centrenergo” in August reported that agreed to only job design, but the project has not yet been ordered, not to mention the physical implementation.

The predecessor of I. Kasalica at the head of the Ministry of coal industry, Vladimir Demchishin, at the end of his term stated that he is ready to take responsibility for the translation of one of the units zmiivska TPP of coal of gas group by the beginning of the autumn-winter season 2016/2017.